National-Level Implementation of the Commission Regulation (EU) 2016/631 of 14/04/2016 Establishing a Network Code on Requirements for Grid Connection of Generators

Main Article Content

J. Rychlak

Abstract







This paper explains the provisions of the network code in the Commission Regulation (EU) 2016/631, known as Network Code Requirements for Generators, and identifies technical and legal conditions related to its implementation at the national level. It specifies, for example, possible concepts of the LFSM automatic control application in the power system defence plan. Based on the National Power System (NPS)’s development scenarios until 2025 and 2030, potential threats to its operation are identified. Issues related to the operation of power system with a high level of wind and PV sources’ penetration are discussed, and the new requirements for generators, which in such conditions are critical for maintaining the power system’s safe operation, are identified.












 



Article Details

How to Cite
J. Rychlak. (2018). National-Level Implementation of the Commission Regulation (EU) 2016/631 of 14/04/2016 Establishing a Network Code on Requirements for Grid Connection of Generators. Acta Energetica, (02), 14–21. https://doi.org/10.52710/ae.112
Section
Articles

References

Network Code for Requirements for Grid Connection Applicable to all Generators, European Network of Transmission System Operators for Electricity, publikacja z dnia 14 kwietnia 2016 r. [online], http://eur-lex.europa.eu/legal- -content/EN/TXT/?uri=uriserv:OJ.L_.2016.112.01.0001.01. ENG&toc=OJ:L:2016:112:TOC [dostęp: 1.03.2017].

Framework Guidelines On Electricity Grid Connections ACER - Agency for the Cooperation of Energy Regulators, 2011.

Electricity in Europe, ENTSOE, 2015 [online], https://www.entsoe.eu/ Documents/Publications/Statistics/ electricity_in_europe/entsoe_electri- city_in_europe_2015_web.pdf [dostęp: 1.03.2017].

Wnioski z analiz prognostycznych na potrzeby Polityki energetycznej Polski do 2050 roku, Załącznik 2. do Polityki energetycznej Polski do 2050 roku, Ministerstwo Gospodarki, 2015 [online], http://bip.me.gov.pl/node/24670 [dostęp: 1.03.2017].

Ierna R. I in., Effects of VSM Convertor Control on Penetration Limits of Non-Synchronous Generation in the GB Power System, 15th Wind Integration Workshop, Vienna, 2016, s. 8.

Scenario Outlook&Adequacy Forecast 2015, ENTSO-E, 2015.

Jansen K., Pfeiffer R., Rychlak J., European Network Codes for Grid Connection, 2016 CIGRÉ USNC International Colloquium Evolution of Power System Planning to Support Connection of Generation, Distributed Resources and Alternative Technologies [online], http:// www.cigre.org [dostęp: 1.03.2017].

ENTSO-E’s Ten Year Network Development Plan (TYNDP), ENTSOE, 2015 [online], https://www.entsoe. eu/Documents/SDC%20documents/ SOAF/150630_SOAF_2015_publication_ wcover.pdf [dostęp: 1.03.2017].

Technical Report on ENTSO-E Network Code: Requirements for Generators, Raport końcowy z dn. 12.11.2013, DNV KEMA Energy and Sustainability [online], https://ec.europa.eu/energy/sites/ener/ files/documents/KEMA_Final%20 Report_RfG%20NC.pdf [dostęp: 1.03.2017].